Tributary Committee Index
Contact Us
|
Project Sponsor:
Chelan
County Natural Resources Department
Funding:
Rocky Reach Tributary Fund
Project Location:
The project area are within two general locations within the mainstem
Entiat River: reaches 2-9 (Slackwater to Potato Moraine, 14.6
river-miles) and 10-11 (Potato Moraine to Preston Creek 7 river-miles).
Project
Description/Purpose:
The project treatments
for the Entiat Habitat Improvements project envisions the placement of
approximately 5 cross vanes in the lower Entiat River reaches 2-9, and
the installation of approximately 5 log retention structures in the
upper middle Entiat. The cross vane installation in the lower Entiat is
intended to increase the amount of pool habitat, increase large woody
debris (LWD) loading, reduce channel confinement, and restore a measure
of riparian function. The log structures in the upper middle Entiat is
intended to increase LWD density, backwater pools, high flow refuge
habitat and tail out habitat and habitat diversity. These measures are
consistent with the Entiat WRIA 46 Management Plan diagnoses for Entiat
spring and late-run Chinook.
Final Report:
Entiat Instream Habitat Improvements, Project 2006-09 RR
|